MEETING OF CLONDALKIN AREA COMMITTEE
Wednesday, June 17, 2015
QUESTION NO.11
QUESTION: Councillor F. Timmons
“To ask the Chief Executive to issue a report on the condition and plans for all 6 approach roads into Clondalkin as a number of potholes are appearing in and around the village. (The roads are : Watery Lane; Ninth Lock Road; Old Nangor Road; Boot Road; Newlands Cross & Monastery Road).”
REPLY:
Recent works has been carried out to the Clondalkin approach roads as follows:
Ninth Lock Road: Resurfaced in late 2013
Old Nangor Road: Footpaths upgrade in 2012. Repairs to surfacing to be carried out in 2015.
Boot Road: Repairs to be carried out in 2015 at the junction with Fonthill Road
Newlands Cross: Recent upgrade scheme completed.
Monastery Road: Footpath upgrade ongoing also Repairs to surfacing to be carried out in 2015.
New Road: Resurfacing carried out in 2014 also further repairs to be carried out in 2015.
Fonthill Road: Resurfacing carried out in 2013 and 2014.
Watery Lane: Road surface is in good condition and no works are scheduled for 2015